Below is a sample list of projects undertaken by Concrete Logistics.

We are happy to porvide more information on specific projects and references where required.
Project Location Client Volume Scope
Mable Bar Floodways Marble Bar / Nullagine Road Main Roads WA 350m3 To construct two concrete floodways. This project was supply and place, which also included all earthworks and traffic control on detours and approaches.
Varanus Island Gas Plant Varanus Island, Indian Ocean Apache Energy 250m3 To supply concrete for minor civil works project.
Jimblebar Non Processing Plant Jimblebar Mine Site WA Wylie & Skene / BHP 1400m3 To supply and place concrete for all infrastructures for the Non processing plant. Included all earthworks, concrete supply and placement.
Nammuldi Train Tunnel Nammuldi Mine Site WA NRW / Rio Tinto 2500m3 To supply concrete for train tunnel infrastructure.
Rom Wall - Design and Construction Cloudbreak Mine Worley Parsons / FMG 18,000m3 Stab Fill
1,500m3 Concrete
To design and construct a pre-cast tilt up panel wall, 160m long x 17m high with mass stabilised backfill. Construct footing, supply and place concrete.
Goldfields Highway Culverts Wiluna WA Main Roads WA 2000m3 To supply and place concrete & stabilised fill around culverts. Includes earthworks and culvert placement.
Moura Mine Infrastructure Moura Mine Site QLD Moura Mine 1000m3 To supply concrete for the civil construction infrastructure projects.
Yule River Bridgeworks Yule River, Port Hedland WA Main Roads WA 730m3 To supply concrete for bridgeworks and abutment construction.
Gull to Tunkawanna Rail Repairs Tom Price to Karratha Road WA Rio Tinto 850m3 To supply concrete and stabilised fill (7% and 10%). Install culverts under damaged rail formation due to floods from cyclone. Includes earthworks, wrapping culverts, culvert installation, concrete and stabilised placement, construction of culvert head / wing walls.
Derby Highway Culverts Derby WA Main Roads WA 400m3 To supply concrete and stabilised backfill for culvert construction.
Yandi Refuelling Infrastructure Yandi Mine Site WA Rio Tinto 1500m3 To construct concrete infrastructure for loco refuelling facilities including detailed earthworks and 3.6km of concrete pipe racks.
Ore Body 18 Ore Body 18 Mine Site WA Wylie & Skene / BHP 400m3 To construct minor infrastructure for the explosives depot. Includes supply and placement of concrete, detailed earthworks.
Lang Hancock Rail Hope Downs Thiess Contracting / Hancock Prospecting / Rio Tinto 10,100m3 To supply concrete and stabilised fill (7% & 10%) for backfilling of culverts and head wall construction.
Parker Point Dump Hopper Back Fill Parker Point, Dampier Monodalphous / Rio Tinto 6000m3 To supply stabilised backfill to fill disused dump hopper.
Red Bank Bridge Abutment Realignment Port Hedland NRW / BHP 1700m3 To realign existing abutment and construct floodway at Harding River. Includes detailed earthworks, concrete supply and placement, concrete batter protection, rock basket construction and placement, head wall construction.
Boodarie Loco Refuelling Facility Boodarie Iron, Port Hedland WA Wylie & Skene / BHP 1000m3 To construct infrastructure for the loco refuelling facility and associated concrete works.
Wharf Pile Filling Cape Lambert (3.1km out to sea) McConnell Dowell / SKM - Rio Tinto 1000m3 To supply iron ore fines concrete and pump into piles at various locations on the dolphins at the end of the wharf. Concrete was supplied and placed off a 500 ton barge.
HOME | ABOUT US | PROJECTS | FLEET | POLICIES | NORTH WEST CONCRETE PRODUCTS & PAVERS | CONTACT